Certification at end of construction 3.14
Due date for completion 3.14.1
Certification of completion 3.15
A Certificate of Completion will be issued by us when all the requirements of the agreement have been satisfied.
The requirements (if applicable), include:
Vesting of works 3.16
We're responsible for the operation and maintenance of the Works and associated costs from the date of the Certificate of Completion, except where costs are incurred as a re
Maintenance agreements 3.17
When a developer is designing and constructing one of our wetlands or retarding basins, often we and the local council are expected to have joint maintenance responsibilities wit
Guidelines, drawings and checklists
We have over 60 standard drawings to help with your development. We also have guidelines to help you identify the minimum requirements to be completed when submitting a range of applications to us.
Checklists and statements
Use our checklists and statement templates to provide us with the right information in your application or to guide development steps.
Drawings
Download a variety of previous standard or concept drawings to assist with your proposed development.
Guidelines
View a range of guidelines to help with your proposed development.
Drainage works objectives
The contemporary engineering approach to drainage is to recognise stormwater is part of the total water cycle.