COVID-19 update: Customers may experience some delays with planning, building and development enquiries and applications. We are working to minimise changes where possible, and thank you for your patience and understanding during this time. For building or development queries please email [email protected] or call our Customer Service Centre on 131 722.

Provision of notice 3.9

​Specified inspections

Where the Agreement specifies witness points, hold points or the like to be observed during construction of works, the consultant must make suitable arrangements with us to enable adequate inspection to take place as may be necessary, at mutually agreed times.

We won't accept works unless specified inspection procedures have been completed to our satisfaction.

Contractor activity

The consultant must:

  • advise us if the contractor vacates the site
  • give us two working days notice prior to the contractor recommencing work.

 