COVID-19 update: Customers may experience some delays with planning, building and development enquiries and applications. We are working to minimise changes where possible, and thank you for your patience and understanding during this time. For building or development queries please email [email protected] or call our Customer Service Centre on 131 722.

Certification of completion 3.15

A Certificate of Completion will be issued by us when all the requirements of the agreement have been satisfied.

The requirements (if applicable), include:

  1. we've issued the Certificate of Practical Completion
  2. all contributions have been paid
  3. all other money to be paid has been paid to us
  4. downstream works have been certified complete or the Owner has made alternative arrangements which are acceptable to us
  5. we've received a copy of the amended plan of subdivision, certified by the council and indicating the easements and/or reserves required to cover all Works
  6. any other information, notices or documents required by us have been provided
  7. the defects liability period has ended to the satisfaction of us
  8. a maintenance agreement is in place (if required)