Hobsons Bay Main Upgrade Project

Icon showing the project status of completed Completed
Spotswood

The Hobsons Bay Main Sewer is a critical part of Melbourne’s sewer network, transferring around 30 percent of Melbourne’s wastewater to the Western Treatment Plant. The existing sewer was first constructed in the 1960s, it is now reaching the end of its service life and requires rehabilitation.

About the project

To stay up to date with this project and others in the Spotswood precinct, join our new Let's talk Spotswood Super Sewage Community Hub.

The sewer is located under the Yarra River between Westgate Park in Port Melbourne and Scienceworks in Spotswood. To rehabilitate the existing sewer, we are building a duplicate sewer which will allow sewage flows to be diverted during rehabilitation works. These critical works form part of a broader Melbourne Water sewer program on a number of ageing sewers around the city.

The current sewer is still functioning and there is no immediate environmental danger, however these critical sewer works are necessary to protect our future and will provide a significant increase in system capacity to cater for Melbourne’s growing population.

This project is part of Melbourne Water’s commitment to protecting Melbourne’s bays and waterways from environmental harm and ensuring the reliability of our sewer network.

Major works from June 2022 to October 2024

The new duplicate Hobsons Bay Main tunnel project was completed in October 2024 and is successfully taking Melbourne's sewage through to the Western Treatment Plant in Werribee.

The relining of the original Hobsons Bay Main Sewer pipeline is currently underway.

 

 

Complete
 

September 2021 - December 2021

Early works and final geotechnical investigations

Complete
 

January 2022 - May 2022

Site mobilisation

Complete
 

June 2022 - April 2023

Main works - piling and shaft construction

Complete
 

May 2023 - August 2023

Main works - shaft excavation

Complete
 

August 2023 - December 2023

Main works - tunnelling works

Complete
 

October 2024

Permanent works and reinstatement of construction areas completed.

The works area

The project works took place on both the east and the west sides of the Yarra River.

HBM Truck Routes
Truck routes during site works.

Contact us

For more information, please contact the Hobsons Bay Main Project Team: 

[email protected]

1800 512 313

Last updated:

Did you find what you were looking for?