Early works and final geotechnical investigations
The Hobsons Bay Main Sewer is a critical part of Melbourne’s sewer network, transferring around 30 percent of Melbourne’s wastewater to the Western Treatment Plant. The existing sewer was first constructed in the 1960s, it is now reaching the end of its service life and requires rehabilitation.
About the project
To stay up to date with this project and others in the Spotswood precinct, join our new Let's talk Spotswood Super Sewage Community Hub.
The sewer is located under the Yarra River between Westgate Park in Port Melbourne and Scienceworks in Spotswood. To rehabilitate the existing sewer, we are building a duplicate sewer which will allow sewage flows to be diverted during rehabilitation works. These critical works form part of a broader Melbourne Water sewer program on a number of ageing sewers around the city.
The current sewer is still functioning and there is no immediate environmental danger, however these critical sewer works are necessary to protect our future and will provide a significant increase in system capacity to cater for Melbourne’s growing population.
This project is part of Melbourne Water’s commitment to protecting Melbourne’s bays and waterways from environmental harm and ensuring the reliability of our sewer network.
Major works from June 2022 to October 2024
Since February 2022, the project team has established two construction sites at Scienceworks and Westgate Park. Tunnelling works have now been completed with tunnel boring machine 'Lucey' completing her 670 metre journey under the Yarra River in November 2023.
Over the coming months works will include:
- Tunnel grouting works
- Sewer connection works to connect the new sewer to the existing network
- Treatment and removal of spoil from site
- Permanent rehabilitation works.
- Project Timeline
September 2021 - December 2021
January 2022 - May 2022
Site mobilisation
June 2022 - April 2023
Main works - piling and shaft construction
May 2023 - August 2023
Main works - shaft excavation
August 2023 - December 2023
Main works - tunnelling works
October 2024
Permanent works and reinstatement of construction areas.
The works area
The project works took place on both the east and the west sides of the Yarra River.
Contact us
For more information, please contact the Hobsons Bay Main Project Team: