Planning and design works
The Quarry Hill tank plays an important role in our water supply network. We need to refurbish the tank so that it can continue to supply high quality water to the local area.
Why is this project important?
The Quarry Hill tank was built in 1978 with an expected design life of 80 years, however inspections and testing of the existing condition of the tank identified refurbishment works are necessary so that it can continue to provide ongoing water supply for now and decades to come.
June 2025 update
The 12-metre high surge tank and upgrade to the main access track have been completed. Yarra Valley Water will now carry out works over the next 12 months. Melbourne Water will return to complete its refurbishment works in mid-2026.
What are we doing?
The works will include:
- upgrading the access track to the tank
- site mobilisation and establishment
- paint removal and restoration
- internal repair work inside the tank
- replacement of the existing roof
- installing new fencing, ladders and external stairways.
Managing impacts
We will make every effort to minimise construction impacts to our neighbours and surrounding community, however, during construction, you may notice:
- Some noise and dust, predominantly during working hours and, particularly when the tank is being cleaned prior to re-painting.
- A crane will be on site to remove and replace the roof structure.
- Installation of the construction site compound with in Melbourne Water's tank site.
- Additional construction vehicles entering and exiting via Findon Road, and an access track on Boral land.
- Construction personnel and activity on the site.
Local water supplies will not be affected by these works.
Keeping you informed
We will provide more information as the project progresses.
Contact the team
1800 413 647
Early - mid 2024
Late October 2024 - Site establishment and mobilisation
Upgrading the access track (Boral property)
November 2024 - mid-2025
Install surge tank
Mid-2025 to mid-2026
Yarra Valley Water will be working on site for the next 12 months
Mid-2026 to mid-2027
Melbourne Water will return to complete refurbishment works