Developers working on assets related to a drainage scheme, known as a Development Services Scheme DSS, or seeking to modify or decommission an existing Melbourne Water asset must apply for our approval of those designs.
Drainage designs go through three stages of review and acceptance:
-
Concept design (follow this link to apply)
-
Functional design (follow this link to apply)
-
Detailed design submission
Note: After obtaining an approved Planning Permit, an accepted Works Offer and approval of the Functional Design, developers can submit Detailed Design Submissions online.
Application process
Documentation requirements
- Detailed design submission
-
- Cultural & Heritage report
- Flora & Fauna report
- Geomorph report (where appropriate)
- Catchment plan/subdivisional staging plan for asset
- Geotech report
- SEMP
- ANCOLD Consequence Assessment report (Retarding Basins only)
- Retarding Basin Design and Assessment Guideline (appendix A) (Retarding Basins only)
- Stormwater Management Strategy (SWMS)
- HECRAS model incl shear stress output (typically Waterways only)
- MUSIC Model (typically Wetlands only)
- Inundation frequency analysis (Typically alternate wetland designs only
- Wetspells analysis (Typically alternate wetland designs only)
- RORB model (Typically Retarding Basins only)
- Planting plan
- Detail Design report (Typically Waterways, RB’s & Wetlands only)
- Draft maintenance Agreement
- Quality Assurance documents (ISO9001 – QMS) Detailed certification statement and Structural Engineer’s certification, if applicable
- Council design & ownership written approval (where appropriate);
- Detailed Design Drawings (Civil &/or planting)
- Groundwater Assessment report
- Topsoil report
- Sodic management plan (where appropriate)
- Site Environment Management Plan SEMP
-
- For construction civil drawings IFC drawings
- Traffic Management Plan
- SEMP
- Pre-commencement (Civil &/or Planting)
-
Pre-commencement documents (Based on asset type and application type, required and optional documents may vary)
- IFC drawings (Civil &/or Planting)
- OH&S Risk Management Plan
- Traffic Management Plan (including relevant authorities approval)
- Construction schedule (Civil &/or planting)
- Civil preconstruction certification statement and checklist (QA Docs)
- Photos (optional)
- Contractor maintenance schedule
- Planting preconstruction certification statement (QA docs)
- Financial
-
The main documents for financial are:
- Evidence confirming the correct lodgement of tenders through Tenders Vic (if project value is >$450K). (email, PDF, receipt etc) (Civil &/or Planting)
- At least three conforming X3 (min) Contractor's tender submissions (PDF, email or excel) (Civil &/or Planting)
- Melbourne Water Tender assessment template filled in with tender information and initial consultant's assessment of reimbursable items with justification and supporting information. (Excel) (Civil &/or Planting)
- Supporting information (Invoices, photos, MW construction oversight report, consultant justification, comparable rates etc)
- Copy of Security and Retention (Bonds/bank guarantees)
- Financial Variations (Tender and Security and Retention lodgement variation)
- Progress reimbursement justification (if being sought)
- Planting commencement of establishment
-
- Commencement of establishment documents (based on Landscape and Civil application type and Asset types, required and optional documents may vary)
- Consultants plant supply self-audit checklist
- Consultants plant installation self-audit checklist
- Consultants Nursery Inspection self-audit checklist (planting only)
- Plant supply delivery dockets
- Photos (optional)
- Contractor maintenance schedule
- Midterm Planting
-
Midterm Planting Documents: (based on Landscape and Civil application type and Asset types, required and optional documents may vary)
- self-audit checklist
- Photos (optional)
- Contractor maintenance schedule
- General Inspection (Civil & Planting)
-
General Inspection Documents: (based on Landscape and Civil application type and Asset types, required and optional documents vary)
- The need for general inspection meeting clearly articulated with the applicant.
- Practical Completion (Civil & Planting)
-
Practical Completion Documents: (based on Landscape and Civil application type and Asset types, required and optional documents may vary)
- Construction certification statement
- As-constructed certification statement
- As-constructed plan set (refer to ‘As constructed’ requirements)
- As-constructed CAD
- ANCOLD supervision construction report GITA level 1 (Retarding Basins only)
Appendix A from Melbourne Water's Retarding Basin guidelines (Retarding Basins only)
- Construction Report (clay liner & backfill compaction test results, photos etc)
- Topsoiling test results & confirmation soil has met MW specifications
- Sediment pond reset supporting information (Evidence it’s been reset (civil only) such as sample results & tipping receipts, photos etc)
- Planting construction certification statement
- Photos (optional)
- Contractor maintenance schedule (Civil &/or Planting)
- Final Completion (Civil & Planting)
-
Final Completion Documents: (based on Landscape and Civil application type and Asset types, required and optional documents may vary)
- Civil EDLP certification statement
- Planting EDLP certification statement
- Photos (optional)
- Endorsed Maintenance Agreement (Landscape only)
Duration
The process steps’ duration represents Melbourne Water’s response time at each stage, excluding any customer response time to requests from the Design & Construction Hub.
Design & Construction Hub Process Steps | Duration |
---|---|
Detailed Design Review Submission |
20 Business days for single asset type |
Detail Design Review Variation | 20 Business days for single asset type 30 Business days for multiple asset types |
Site Environment Management Plan SEMP | 30 Business days |
SEMP Variation | 30 Business days |
Financial | 33 Business days |
Financial Variation | 35 Business days |
Progress Reimbursement | 35 Business days |
Commencement of Establishment | 28 Business days |
Pre-Commencement | 28 Business days |
General Inspection | 15 Business days |
Practical Completion | 53 Business days |
Midterm Planting | 35 Business days |
Final Completion | 53 Business days |
Fees
There are no fees for this service.