Melbourne Water is renewing the last two kilometre section of the M102 water main. To secure a reliable water supply for the growing suburbs in western Melbourne these essential works will occur between Paramount Road, West Footscray and Williamstown Road, Yarraville from July 2018.

Project update - August 2018

Work commenced

Construction of the West Footscray to Yarraville Water Main (M102) Renewal Project began early July. Starting at the intersection of paramount and Somerville Roads construction activity is moving east along Somerville Road and will turn into Kororoit Street during August.

A crossing of the Princess Highway/Geelong Road is scheduled to take place over two weekends in August/September.

Initial closure: From 7pm Friday 31 August until 5am Monday 3 September 2018. Eastbound (City) lanes will be closed at Kororoit Street, 220m west of Somerville Road. Traffic will be diverted onto the westbound lanes for approximately 300m. Westbound traffic will be limited to two lanes through the work zone.

Second closure : From 7pm Friday 7 September until 5am 10 September 2018. Westbound (Geelong) lanes will be closed from Angliss Street, 200m west of Somerville Road. Traffic will be diverted onto eastbound lanes for approximately 300m. Eastbound traffic will be limited to two lanes through the work zone.

To prepare for the weekend works, one lane of the Princes Highway eastbound will be closed wesbound at Angliss Street between 7am and 5pm on 4 and 5 September 2018.

Local residents and businesses will be provided with information as to how the works may impact them. General information on the two road closures is available as a download below.

Speed limits will be reduced to 40km/h through the work zones. Motorists are advised to plan their journey and allow extra time for travel.

Image showing the lane closures along Princes Highway

After the Geelong Road crossing, works for Stage 1 will finish at the corner of Angliss Street and Kidman Street.

Remaining works:

  • Section 2: From the intersection of Angliss Street and Kidman Street, works will continue east along Kidman Street, across Roberts Street and into Charlotte Street. Moving through Cruickshank Park and across Stony Creek, construction will then travel north along Julian Street and finish at the Somerville Road intersection. These works will begin late September 2018.
  • Section 3: Beginning at Julian Street, works will progress east along Somerville Road to Queensville Street. Some construction is also planned near Severn Street to connect with other water mains. Works will start from January 2019.

Works to lay the new pipeline should be completed by February 2019, with crew to carry-out connection and decommissioning works from March 2019. Completion of works is expected by July 2019, weather permitting.

Melbourne Water is working with John Holland-KBR Joint Venture (JH-KBR JV) as its construction partner to deliver the West Footscray to Yarraville Water Main (M102) Renewal Project. The JH-KBR JV project team has extensive experience in delivering major pipeline renewal projects for Melbourne Water, including the previous stages of the new M102 Water Main from Essendon to West Footscray in recent years.
 

Map showing the areas of work along Somerville Road for the  M102 Water Main Renewal Project

What's happening and when

Work to renew the M102 water main involves:

  • constructing a new 900mm diameter water main through approximately two kilometres of local streets between Paramount Road, West Footscray and Williamstown Road, Yarraville
  • reinstating the area as close as possible to pre-construction condition
  • decommissioning the existing 80 year old M102 water main that runs under Somerville Road.

Timeline

Stage Estimated timing Description
Site investigations

Early 2017 to mid 2017

Locating underground services
Understanding ground conditions
Procurement Late 2017 Project is put to tender
Preferred construction partner chosen
Site mobilisation May 2018 Set-up of site offices
Machinery and equipment delivered to site
Construction starts July 2018 main construction activity to renew M102 Water Main
Pipe construction complete February 2019 Laying of new pipes completed along alignment - ready for connections to other water main infrastructure
Connections and decommissioning March 2019 to May 2019

Construction activity to connect renewed M102 water main into the wider system
Decommissioning of existing M102

Construction complete Mid 2019 Project completion
Final reinstatement of project and surrounding infrastructure

Impacts on local residents and visitors

Like any major project, there will be impacts associated with the renewal of the M102 water main. We are working closely with Maribyrnong City Council, VicRoads and the local community to manage these impacts.

Dig, Lay, Bury methodology and reinstatement will take place progressively as the pipes are installed. The work area will continuously move so that works will only be at any one location for a short period of time before moving on to the next section.

Works will take place along major roads and residential streets. There will be some temporary changes to traffic conditions, parking, access and bicycle routes (see map below).

Comprehensive Traffic Management Plans will be implemented to manage these impacts, and we will notify residents and businesses in advance of the expected changes. Melbourne Water is also working with the West Gate Tunnel project team to ensure coordination across projects, especially when it comes to traffic impacts.

There will be some noise, dust and vibration associated with the construction works. We will continue to work closely with our appointed contractor to minimise these impacts, especially when working in residential streets. Engagement with residents and businesses commenced in December 2016 and will continue throughout the project to help manage any potential impacts.

During construction the majority of works will take place from Monday to Friday between 7am and 6pm, and on Saturday between 7am and 1pm (when required). Outside of these times, quiet activities such as cleaning-up or office duties will be undertaken.

Melbourne Water and the project team thank you in advance for your patience as we carry out this essential upgrade work to help secure water supplies for years to come.

Map showing alternate bike route during the M102 Main Water Renewal project

Why is this project important?

The M102 water main has been in operation for over 80 years and is a critical part of Melbourne's water supply network, supplying the areas of Footscray, Altona and Werribee.

Recent inspections of the existing water main have revealed that the pipeline is at the end of its operational life and needs to be upgraded to meet Melbourne Water’s service standards. This will also secure a reliable water supply for the growing west.

To date, we have completed three separate projects to renew 13 kilometres of the 15 kilometre M102 pipeline. The West Footscray to Yarraville Water Main Renewal project will involve renewing the last two kilometres of this pipeline between Paramount Road, West Footscray and Williamstown Road, Yarraville.

Keeping you informed

We will keep local residents and businesses informed about the works through letters, newsletters, door knocks and web updates.

Your feedback

If you have any questions or want to learn more about this project, please get in touch.

Last updated:
24 August 2018